Page 85 - Urban Renewal Authority 2023-24 Annual Report
P. 85

Site Information before Development  Project Development Information  Project Development Information              Chairman’s Statement
                                 Public
 Project Site   Existing   Residential   Residential   Commercial  Other Uses   G/IC
 Project   Launch   Launch   Development   Building   Total GFA   Open
 Code  Project Name  Year  Month  Name  Area   GFA   Blocks  Population  Flats   m 2  GFA   GFA   GFA   GFA   Space     Remarks  Status
                                   (1)
 m 2  m 2  Number  m 2  m 2  m 2  m 2
                                 m 2
                                                                       Occupation Permit issued on 14-03-23
 Reclamation Street /
 33  YTM-010  2011/12  February  One Soho  1,640  10,024  20  637  322  12,507  10,422  2,085  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Certificate of Compliance issued on 20-07-23
 Shantung Street, Mong Kok
                                                                       Sale of remaining flats in progress
                                                                       Occupation Permit issued on 12-07-19         Managing Director’s Statement
 Pak Tai Street /
 34  KC-006  2010/11  March  Downtown 38  1,277  6,389  12  296  228  9,783  8,152  1,631  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Certificate of Compliance issued on 24-03-20
 San Shan Road, Ma Tau Kok
                                                                       Sale of remaining flats in progress
                                                                       Occupation Permit issued on 08-03-18
 35  SSP/3/001  Shun Ning Road, Sham Shui Po  2009/10  June  The Ascent  825  3,820  8  130  157  7,159  5,959  1,200  0  0  0  Certificate of Compliance issued on 27-07-18
                                                                       Sale of shops in progress
                                                                       Occupation Permit issued on 07-05-19
 Shanghai Street /   618 Shanghai     Rezoned “Other Specified Uses” annotated “Historic Buildings
 36  (6)  MK/01  2008/09  September  1,128  3,944  14  157  0  5,223  0  5,223  0  0  0  Certificate of Compliance issued on 05-07-19
 Argyle Street, Mong Kok  Street      Preserved for Commercial and/or Cultural Uses”
                                                                       Operation commenced in November 2019
 Prince Edward Road West /            Rezoned “Other Specified Uses” annotated “Historic Buildings   Renovation works of acquired properties completed
 37  (6)  MK/02  2008/09  September  1,440  4,334  10  31  0  4,334  0  4,334  0  0  0
 Yuen Ngai Street, Mong Kok           Preserved for Commercial and/or Cultural Uses”  Renovated units leased out
                                                                       Occupation Permit issued on 25-05-17         Operating Review
 Chi Kiang Street /
 38  TKW/1/001  2007/08  February  City Hub  931  5,226  10  302  175  8,378  6,980  1,398  0  0  0  Certificate of Compliance issued on 15-01-18
 Ha Heung Road, Ma Tau Kok
                                                                       Sale of remaining flats in progress
                                                                       Site clearance completed on 26-01-16
                                      At-grade Conservation Park accessible to public will be provided.
                                      The village gatehouse, the embedded stone tablet and the Tin Hau   An enhanced conservation proposal reported to AAB in 12-22 with support
 39  (2,5)  K1  Nga Tsin Wai Village, Wong Tai Sin  2007/08  October  6,013  2,051  116  124  750  37,097  34,778  2,319  0  0  0  Temple, as well as the central axis that connects them, and the   obtained
                                      foundation remains of old village walls and watchtowers will be   Land Grant executed on 21-06-23
                                      preserved                        Demolition and hoarding site works in progress
                                                                       Archaeological Rescue Excavation works in progress
                                                                       Site A
                                                                       Pre-sale consent issued on 22-11-21
                                                                       Superstructure works in progress             Corporate Sustainability
 One Central
 Place                                A 1,260m  multi-purpose activity hall for community use will be
                                          2
 Peel Street /   (Site A)                                              Site B
 40  (2,5)  H18  2007/08  July  5,267  20,219  47  740  306  67,402  22,638  43,294  210  1,260  2,138  provided at Site A. Commercial space includes a Market Block at    Occupation Permit obtained on 28-12-18
 Graham Street, Sheung Wan            Site B                           Certificate of Compliance obtained on 20-06-19
 My Central                                                            Completed in 2020-21
 (Site B)
                                                                       Site C
                                                                       Main contract works in progress
                                                                       YWS Site (DA 1)
                                                                       Occupation Permit obtained on 08-07-14
                                                                       Certificate of Compliance obtained on 29-10-14
                                                                       Completed in 2021-22
                                                                 2
                                                      2
                                      Commercial GFA include 66,000m  for offices and 10,000m  for hotel Main Site (DAs 2 & 3)
                                                2
                                      G/IC includes 6,200m  for Kwun Tong Jockey Club Health Centre in   Occupation Permit issued on 26-11-20  Management Discussion and Analysis
 Park                                           2                      Certificate of Compliance issued on 28-04-21
 Metropolitan                         YWS Site and 17,200m  for Government uses in Main Site and   All flats sold
                                          2
 Kwun Tong Town Centre,   (DA 1)      16,316m  for Public Transport Interchange (PTI) in Main Site
 41  (2)  K7  2006/07  March  53,500  96,104  63  3,139  4,048  468,330  270,710  157,904  0  39,716  18,376  Commercial Space includes 1,300m  for social enterprises
                                                      2
 Kwun Tong
 Grand Central                        Residential flats include 299 flats in Yuet Wah Street site, 1,999 flats in  Main Site (DAs 4 & 5)
                                                                       Site clearance of DA 4 completed on 31-03-21
 (DAs 2&3)                            the Main Site (DAs 2 & 3) and 1,750 in the Main Site (DAs 4 & 5)
                                                          2
                                      Public space includes a minimum of 9,600m  at-grade public open   Site clearance of DA 5 completed on 17-05-21
                                              2
                                      space and 8,776m  podium public open space  Demolition works completed
                                                                       A revised DSP based on “Vertical City” planning concept submitted to TPB
                                                                       The revised DSP gazetted on 08-12-23 for a 2-month public consultation
                                                                       TPB hearing for comments on revised DSP held on 26-04-24 and TPB agreed to
                                                                       submit the DSP for CE-in-C’s approval
                                                                       The site is being temporarily used for sports and other community activities
                                      Three projects taken forward as one  Occupation Permit (Site A) issued on 07-06-21
 42  Hai Tan Street /                 G/IC includes 1,900m  for Special Child Care Centre cum Early   Occupation Permit (Site B) issued on 10-06-21  Projects at a Glance
                                                2
 43  SSP/1/003-  Kweilin Street &   2005/06  February  Seaside Sonata  7,507  25,344  70  1,589  876  57,399  50,024  5,317  0  2,058  1,500  Education Centre, Day Care Centre for Elderly and Sub-base for a   Occupation Permit (Site C) issued on 06-07-21
                                                       2
 44  005  Pei Ho Street, Sham Shui Po  Neighbourhood Elderly Centre; 150m  for either social enterprise or  Certificate of Compliance issued on 26-10-21
                                      non-domestic use                 Sale of shops in progress
                                      Rezoned “Other Specified Uses” annotated “Open Space and
 Mallory Street /                     Historical Buildings Preserved for Cultural and Commercial Uses”  Occupation Permit issued on 20-05-13
 45  (7)  WC/001  2004/05  March  M7  780  2,687  10  122  0  2,435  0  0  2,435  0  300  Certificate of Compliance issued on 04-08-17
 Burrows Street, Wan Chai             GFA includes retained façade at Burrows Street and two elevated
                                      walkways                         URA took over the management and operation of the project in August 2018
                                                                       Occupation Permit issued on 20-09-12
 Pine Street /
 46  K32  2004/05  December  Park Summit  2,328  11,802  30  518  462  20,952  17,460  3,492  0  0  450  Public Open Space not required under lease  Certificate of Compliance issued on 27-12-12
 Anchor Street, Tai Kok Tsui
                                                                       Sale of shops in progress                    Corporate Governance