Page 83 - Urban Renewal Authority 2023-24 Annual Report
P. 83

Site Information before Development  Project Development Information  Project Development Information              Chairman’s Statement
                                 Public
 Project Site   Existing   Residential   Residential   Commercial  Other Uses   G/IC
 Project   Launch   Launch   Development   Building   Total GFA   Open
                                   (1)
 Code  Project Name  Year  Month  Name  Area   GFA   Blocks  Population  Flats   m 2  GFA   GFA   GFA   GFA   Space     Remarks  Status
 m 2  m 2  Number  m 2  m 2  m 2  m 2
                                 m 2
 Wing Kwong Street /
 13  (2)  KC-014  2018/19  June  3,016  16,874  36  831  506  25,884  21,570  4,314  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Foundation works in progress
 Sung On Street, To Kwa Wan
 Oak Street /
 14  (2)  YTM-011  2017/18  March  820  2,999  6  205  122  5,571  4,642  929  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Main contract works in progress
 Ivy Street, Tai Kok Tsui                                                                                           Managing Director’s Statement
 Queen’s Road West /
 15  (2)  C&W-006  2017/18  March  2,046  4,107  6  160  231  11,992  10,381  432  0  1,178  538  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Foundation works in progress
 In Ku Lane, Sai Ying Pun
 Sung Hing Lane /
 16  (2)  C&W-005  2017/18  July  1,120  3,984  9  231  210  8,740  8,478  262  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Foundation works in progress
 Kwai Heung Street, Sai Ying Pun
                                      Eligible domestic owner-occupiers can join the Flat-for-Flat scheme
 Kai Ming Street /
 17  (2)  KC-013  2016/17  March  1,749  7,458  12  463  472  22,419  18,682  3,737  0  0  0  Project KC-013 has combined with Project KC-012 for development   Foundation works in progress
 Wing Kwong Street, To Kwa Wan
                                      under a single land grant
                                      Eligible domestic owner-occupiers can join the Flat-for-Flat scheme
                                      Project KC-012 has combined with Project KC-013 for development
 18  (2)  KC-012  Wing Kwong Street, To Kwa Wan  2016/17  June  1,258  5,023  14  388  See Remarks  See Remarks  Foundation works in progress
                                      under a single land grant (please refer to Project KC-013 for the
                                      details of development parameters)                                            Operating Review
                                      Eligible domestic owner-occupiers can join the Flat-for-Flat scheme
 Hung Fook Street /
 19  (2)  KC-011  2016/17  June  2,635  12,628  23  813  564  26,523  22,102  3,871  0  550  0  Project KC-011 has combined with Project DL-8:KC for development  Foundation works in progress
 Kai Ming Street, To Kwa Wan
                                      under a single land grant
 Hung Fook Street /
 20  (2)  KC-010  2016/17  June  4,951  21,495  43  1,468  669  41,229  34,357  6,872  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Foundation works in progress
 Ngan Hon Street, To Kwa Wan
                                      Eligible domestic owner-occupiers can join the Flat-for-Flat scheme
 Chun Tin Street /   eResidence                                        Main contract works in progress
 21  (2)  KC-008(A)  2016/17  May  2,475  3,738  14  179  260  13,841  12,270  1,571  0  0  0  The project is developed by URA and all 260 flats are sold as Starter
 Sung Chi Street, To Kwa Wan  Tower 3                                  Starter Homes Flat selection completed on 28-03-24 and 173 flats sold
                                      Homes
 Bailey Street /
 22  (2)  KC-009  2015/16  March  8,042  39,644  94  2,640  1,296  66,654  55,545  11,109  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Foundation works in progress
 Wing Kwong Street, To Kwa Wan                                                                                      Corporate Sustainability
                                      Eligible domestic owner-occupiers can join the Flat-for-Flat scheme
 23  (2,3)  DL-11:YTM  Ash Street, Tai Kok Tsui  2015/16  May  474  3,228  5  206  61  2,896  2,828  0  68  0  0  Foundation works in progress
                                      The project is developed by URA
                                                                       Occupation Permit issued on 26-10-23
 24  (3)  DL-10:KT  Hang On Street, Kwun Tong  2014/15  November  Bal Residence  865  5,304  10  387  156  6,661  5,920  222  0  519  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Certificate of Compliance issued on 22-03-24
                                                                       Sale of remaining flats in progress
                                                                       Occupation Permit issued on 03-11-22
 Castle Peak Road /
 25  SSP-016  2013/14  February  The Harmonie  1,900  7,335  16  476  337  14,841  12,367  2,474  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Certificate of Compliance issued on 12-06-23
 Un Chau Street, Sham Shui Po
                                                                       Sale of remaining flats in progress
                                      Eligible domestic owner-occupiers can join the Flat-for-Flat scheme
                                      Project DL-8:KC has combined with Project KC-011 for development
 26  (2,3)  DL-8:KC  Kai Ming Street, To Kwa Wan  2013/14  December  553  2,467  6  122  See Remarks  See Remarks  Foundation works in progress
                                      under a single land grant (Please refer to Project KC-011 for the
                                      details of development parameters)
                                                                       Occupation Permit issued on 20-05-21
 Fuk Chak Street /
 27  (3)  DL-6:YTM  2013/14  June  Sablier  769  3,461  2  171  144  5,738  5,101  637  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Certificate of Compliance issued on 28-09-21  Management Discussion and Analysis
 Li Tak Street, Tai Kok Tsui
                                                                       Sale of remaining flats in progress
                                                                       Pre-sale consent issued on 16-05-22
 Tung Chau Street /
 28  (3)  DL-5:SSP  2013/14  April  The Symphonie  1,490  10,313  1  552  262  13,409  9,355  4,054  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Occupation Permit issued on 12-06-23
 Kweilin Street, Sham Shui Po
                                                                       Certificate of Compliance issued on 29-11-23
                                                                       Occupation Permit issued on 20-05-20
 Kowloon Road /
 29  (3)  DL-4:SSP  2013/14  April  Madison Park  599  3,817  1  229  100  4,884  4,070  814  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Certificate of Compliance issued on 09-11-20
 Kiu Yam Street, Sham Shui Po
                                                                       Leasing of shops in progress
                                      Eligible domestic owner-occupiers can join the Flat-for-Flat scheme
 Tonkin Street /                                                       Pre-sale consent issued on 27-02-24
 30  (2)  SSP-015  2012/13  March  1,268  4,964  13  270  198  9,675  8,062  1,613  0  0  0  The Joint Venture Partner has adopted the Modular Integrated
 Fuk Wing Street, Sham Shui Po                                         Superstructure works in progress
                                      Construction method for the project
                                                                       Retrofitting works for acquired properties and common areas of the project
 Yu Chau West Street,                                                  completed in 11-21
 31  (4,8)  IB-2:SSP  2012/13  January  1,393  12,145  1  0  0  12,145  0  12,145  0  0  0  The project is switched from redevelopment to retrofitting
 Cheung Sha Wan                                                        The refurbished premises occupied by URA, a social enterprise and NGOs  Projects at a Glance
                                                                       Notification of Withdrawal of IB-2:SSP gazetted on 26-08-22
                                                                       Occupation Permit issued on 30-09-21
 Pine Street /
 32  (3)  DL-3:YTM  2012/13  April  L  • Living 23  865  5,105  11  330  142  6,597  5,608  989  0  0  0  Eligible domestic owner-occupiers can join the Flat-for-Flat scheme  Certificate of Compliance obtained on 22-12-21
 Oak Street, Tai Kok Tsui
                                                                       Sale of remaining flats in progress