Page 85 - URA Annual Report 2020-21
P. 85

     Commercial
GFA m2
Other Uses
GFA m2
0
G/IC
GFA m2
0
Public
Open
Space (2) m2
Remarks
           16,716
0
0
0
The project is switched from redevelopment to retrofitting
Project commencement gazetted on 18-01-13
SDEV authorised URA to proceed on 08-08-13
Initial acquisition offer issued on 17-12-13
Retrofitting works for acquired properties and common areas of the project in progress
      405
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Pre-sale consent issued on 29-11-17
Sales of residential flats launched on 15-12-17 Occupation Permit issued on 31-12-18 Certificate of Compliance issued on 03-04-19 Sale of remaining flats in progress
          468
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Occupation Permit issued on 09-04-20 Pre-sale consent issued on 12-06-20
Sales of residential flats launched on 31-08-20 Certificate of Compliance issued on 18-12-20 Sale of remaining flats in progress
          989
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Joint Venture Development tender awarded on 14-06-16 Land Grant executed on 08-08-16
Site handed over to JVP on 04-10-16
Pre-sale consent issued on 22-08-19
Sales of residential flats launched in 04-21 GBP amendment approved on 12-04-21 Superstructure works in progress
          2,085
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Small sized flats of 35 to 65m2
Joint Venture Development tender awarded on 18-12-17 Land Grant executed on 08-03-18
Site handed over to JVP on 18-04-18
GBP amendment approved on 18-02-21
Superstructure works in progress
Presale consent issued on 20-04-21
Sales of residential flats launched on 21-04-21
      2,076
0
 952
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Small sized flats of 35 to 65m2
    559
0
0
0
No less than 50% of residential units should be small flats equal to or smaller than 45m2
Eligible domestic owner-occupiers can join Flat for Flat scheme
          1,631
0
0
0
Small sized flats of 25 to 36m2
Eligible domestic owner-occupiers can join Flat for Flat scheme
Presale consent issued on 28-09-18
Sales of residential flats launched on 15-01-19 Occupation Permit issued on 12-07-19 Certificate of Compliance issued on 24-03-20 Sale of remaining flats in progress
          3,114
500
Project commenced at request of Government following collapse of one building and demolition of damaged adjacent one
Other uses GFA for community use (e.g. social enterprise)
The project was developed by URA
All 493 flats were assigned for sale as “Starter Homes”
Land Grant executed on 13-04-15
Modification Letter for “Starter Homes” executed on 14-11-18 Occupation Permit issued on 02-09-19
Certificate of Compliance issued on 28-04-20
All the 493 Starter Homes units sold
      1,200
0
0
0
     5,223
0
0
0
Zoned ‘Other Specified Uses’ annotated ‘Historic Buildings Preserved for Commercial and/or Cultural Uses’
     6,126
0
0
0
Zoned ‘Other Specified Uses’ annotated ‘Historic Buildings Preserved for Commercial and/or Cultural Uses’
         1,398
0
0
0
Pre-sale consent issued on 23-8-16 Occupation Permit issued on 25-05-17 Certificate of Compliance issued on 15-01-18 Sales of residential flats launched on 04-02-18 Sales of remaining flats in progress
           Project Development Information
  Status
 Presale consent issued on 17-01-19
Sales of residential flats launched on 19-03-19 Occupation Permit issued on 15-09-20 Certificate of Compliance issued on 08-03-21
Presale consent issued on 25-07-17
Sales of residential flats launched in 09-17 Occupation Permit issued on 16-08-18 Certificate of Compliance issued on 28-12-18
Presale consent issued on 19-04-16
Sales of residential flats launched on 17-07-16 Occupation Permit issued on 08-03-18 Certificate of Compliance issued on 27-07-18
Land Grant executed on 25-01-17 Occupation Permit issued on 07-05-19 Certificate of Compliance issued on 05-07-19 Operation commenced in 11-19
Renovation works of acquired properties completed Renovated units leased out
    URA ANNUAL REPORT 2020-21 81