Page 83 - URA Annual Report 2020-21
P. 83

     Commercial
GFA m2
Other Uses
GFA m2
G/IC
GFA m2
Public
Open
Space (2) m2
Remarks
           6,843
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Project commencement gazetted on 03-06-16 DSP approved by CE in C on 31-10-17
Initial acquisition offers issued on 06-12-17 Resumption gazetted on 06-09-19
Site reverted to Government on 07-12-19 Clearance works in progress
          1,447
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
The project will be developed by URA and all 260 flats will be sold as “Starter Homes”
Project commencement gazetted on 06-05-16
Initial acquisition offers issued on 05-07-16 under special arrangement DSP approved by CE in C on 31-10-17
Second round acquisition offers issued on 06-12-17
Resumption gazetted on 06-09-19
Site reverted to Government on 07-12-19
Site clearance completed on 30-11-20
Land Grant executed on 30-06-21
Demolition works completed and utility diversion in progress
         11,105
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Project commencement gazetted on 04-03-16
SDEV authorised URA to proceed on 25-11-16
Initial acquisition offers issued on 07-07-17
S.16 approval for provision of underground public carpark granted by TPB on 21-12-18
Resumption gazetted on 06-09-19
Site reverted to Government on 07-12-19 Site clearance completed on 30-06-21
      466
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
The project is developed by URA
          222
0
519
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Joint Venture Development tender awarded on 30-04-19 Demolition works completed
Site was handed over to JVP on 09-08-19
Main contract works in progress
GBP amendment approved on 07-04-21
          2,474
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Joint Venture Development tender awarded on 23-10-18 Site handed over to JVP on 22-11-18
Land Grant executed on 24-01-19
GBP amendment approved on 17-03-21
Superstructure works in progress
          308
0
450
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
The project will combine with KC-011 for tender
Project commencement gazetted on 19-12-13
Provisional basic terms offer was accepted by URA on 03-07-15 Site clearance completed on 10-07-15
Demolition works completed
STT application for temporary open space submitted on 01-03-17
          637
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Joint Venture Development tender awarded on 13-06-17 Land Grant executed on 07-09-17
Site handed over to JVP on 07-09-17
Pre-sale consent issued on 01-09-20
Sales of residential flats launched on 02-10-20 Occupation Permit issued on 20-05-21
Fitting out works in progress
          814
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Pre-sale consent was issued on 08-08-18 Sales of residential flats launched on 29-08-18 Occupation Permit issued on 20-05-20 Certificate of Compliance issued on 09-11-20 Sale of remaining flats in progress
          4,054
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Joint Venture Development tender awarded on 12-06-18 Land Grant executed on 21-08-18
Site handed over to JVP on 21-08-18
GBP amendment approved on 16-07-20
Superstructure works in progress
      1,613
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
          Project Development Information
  Status
 Land Grant executed on 25-03-19 Foundation works in progress GBP approved on 09-10-20
Joint Venture Development tender awarded on 23-04-20 Land grant was executed on 02-07-20
Site was handed over to JVP on 12-08-20
Foundation works in progress