Page 81 - URA Annual Report 2020-21
P. 81

     Commercial
GFA m2
Other Uses
GFA m2
G/IC
GFA m2
Public
Open
Space (2) m2
Remarks
           8,322
0
5,548
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
     2,490
0
2,850
980
Eligible domestic owner-occupiers can join the Flat for Flat scheme
          6,449
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Project commencement gazetted on 22-05-20
SDEV authorised URA to proceed on 03-02-21
Objectors lodged appeals against SDEV’s authorisation
Appeal Board hearing held on 16-04-21 and Appeal Board decided to dismiss the appeals
Decision of Appeal Board gazetted on 18-06-21
      10,082
0
2,150
400
    7,228
0
800
1,000
Eligible domestic owner-occupiers can join the Flat for Flat scheme
 Eligible domestic owner-occupiers can join the Flat for Flat scheme
          4,286
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Project commencement gazetted on 22-06-18 SDEV authorised URA to proceed on 18-02-19 Initial acquisition offers issued on 03-05-19 Resumption gazetted on 26-02-21
Site reverted to Government on 27-05-21 Clearance works in progress
          998
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Project commencement gazetted on 16-03-18 SDEV authorised URA to proceed on 19-11-18 Initial acquisition offers issued on 30-11-18 Resumption gazetted on 04-09-20
Site reverted to Government on 05-12-20
Clearance works in progress
Joint Venture Development tender awarded on 10-06-21
          540
0
1,060
538
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Project commencement gazetted on 16-03-18 DSP approved by CE in C on 09-07-19
Initial acquisition offers issued on 02-08-19 Resumption gazetted on 26-02-21
Site reverted to Government on 27-05-21 Clearance works in progress
          400
0
150
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Project commencement gazetted on 28-07-17 SDEV authorised URA to proceed on 23-03-18 Initial acquisition offers issued on 14-05-18 Resumption gazetted on 04-09-20
Site reverted to Government on 05-12-20 Clearance works in progress
    0
0
      1,967
0
0
Project KC-013 will combine with KC-012 with a flat production of 414 for the combined site
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Project commencement gazetted on 17-03-17 SDEV authorised URA to proceed on 13-10-17 Initial acquisition offers issued on 06-12-17 Resumption gazetted on 06-09-19
Site reverted to Government on 07-12-19 Site clearance completed on 08-12-20 Demolition works in progress
      1,755
0
0
0
Project KC-012 will combine with KC-013 with a flat production of 414 for the combined site
Eligible domestic owner-occupiers can join the Flat for Flat scheme
Project commencement gazetted on 03-06-16 SDEV authorised URA to proceed on 10-03-17 Initial acquisition offers issued on 07-07-17 Resumption gazetted on 06-09-19
Site reverted to Government on 07-12-19 Site clearance completed on 10-06-21
      3,660
0
0
0
Eligible domestic owner-occupiers can join the Flat for Flat scheme
The project will combine with DL-8 for tender
Project commencement gazetted on 03-06-16 SDEV authorised URA to proceed on 03-03-17 Initial acquisition offers issued on 07-07-17 Resumption gazetted on 06-09-19
Site reverted to Government on 07-12-19 Clearance works in progress
           Project Development Information
  Status
Project commencement gazetted on 05-03-21 Project commencement gazetted on 16-10-20
Project commencement gazetted on 22-05-20 Draft DSP submitted to TPB on 22-05-20
Project commencement gazetted on 22-02-19 DSP approved by CE in C on 29-09-20
Initial acquisition offers issued on 19-10-20
       URA ANNUAL REPORT 2020-21 77