Page 95 - URA Annual Report 2021-22
P. 95
Commercial
GFA m2
Other Uses
GFA m2
G/IC
GFA m2
Public
Open
Space (1) m2
Remarks
1,200
0
0
0
5,223
6,126
0
0
0
0
0
0
Zoned ‘Other Specified Uses’ annotated ‘Historic Buildings Preserved for Commercial and/or Cultural Uses’
Zoned ‘Other Specified Uses’ annotated ‘Historic Buildings Preserved for Commercial and/or Cultural Uses’
1,398
0
0
0
2,319
0
0
0
At-grade conservation park accessible to public will
be provided. Commercial space includes preserved buildings/elements, temple office, village committee’s office, reprovisioning of Public Toilet and other covered areas but actual area still subject to detailed design
Site clearance completed on 26-01-16
Further excavation and field investigation works conducted between 2019 and 2021 to update and ascertain the findings on heritage significance and areas for preservation and future rescue excavation
An enhanced conservation proposal submitted to AMO in 02-22 for consideration
43,294
210
1,260
2,142
G/IC is a 1,260m2 multi-purpose activity hall at Site B Commercial space includes a Market Block at Site B, office space and 9,159m2 for hotel; 210m2 non-domestic GFA is used for the covered Public Open Space at
Site A
Site A
Pre-sale consent issued on 22-11-21 Superstructure works in progress
Site B
Occupation Permit issued on 28-12-18 Certificate of Compliance issued on 20-06-19 Completed in 2020-21
Site C
Foundation works in progress
209,523
0
31,117
13,350
Commercial GFA includes 65,860m2 for offices and 32,000m2 for hotel
G/IC includes 6,200m2 for Kwun Tong Jockey Club Health Centre in YWS Site and 8,601m2 for Government uses in Main Site and 16,316m2 for Public Transport Interchange (PTI) in Main Site
Commercial Space includes 1,300m2 for social enterprises
Residential flats include 299 flats in Yuet Wah Street site and 1,999 flats in the Main Site (DAs 2 & 3)
Public space includes a minimum of 9,350m2 at-grade public open space as required under the approved S16 A/K14/745 and a minimum of 4,000m2 podium public open space as required under the lease
YWS Site (DA 1)
Occupation Permit issued on 08-07-14 Certificate of Compliance issued on 29-10-14 Completed in 2021-22
Main Site (DAs 2 & 3)
Occupation Permit issued on 26-11-20
PTI started operation on 02-04-21
Certificate of Compliance issued on 28-04-21 Sale of remaining flats in progress
Main Site (DAs 4 & 5)
Site clearance of DA 4 completed on 31-03-21
Site clearance of DA 5 completed on 17-05-21
Demolition works completed
A fresh S16 application for floating planning parameters submitted to TPB on 15-07-22
5,317
0
2,058
1,500
Three projects taken forward as one
G/IC includes 1,900m2 for Special Child Care Centre cum Early Education Centre, Day Care Centre for Elderly and Sub-base for a Neighbourhood Elderly Centre; 150m2 for either social enterprise or non-domestic use
Occupation Permit (Site A) issued on 07-06-21 Occupation Permit (Site B) issued on 10-06-21 Occupation Permit (Site C) issued on 06-07-21 Certificate of Compliance issued on 26-10-21 Sale of remaining flats in progress
0
0
0
0
Project Development Information
Status
Occupation Permit issued on 08-03-18 Certificate of Compliance issued on 27-07-18 Sale of shops in progress
Occupation Permit issued on 07-05-19 Certificate of Compliance issued on 05-07-19 Operation commenced in 11-19
Renovation works of acquired properties completed Renovated units leased out
Occupation Permit issued on 25-05-17 Certificate of Compliance issued on 15-01-18 Sale of remaining flats in progress
Occupation Permit issued on 28-10-19 Certificate of Compliance issued on 30-03-20 Sale of remaining flats in progress